Leesburg Committee Notes: January, 9 2024

Chair: Jessee Maloney 

Makersmiths Members Present:  

  • Christa S.
  • John Carter
  • Scott Silvers
  • Brad Hess
  • Jason Gilligan
  • Maggie Gilligan
  • Tim Cotter
  • Bryan Boston
  • Jason McCoy
  • Becky McCoy
  • Jennifer Chu
  • Ken F.
  • Mark Millsap
    • Storing Marketing Materials - eventually Utility Closet
    • Storing Vacuums - Maybe Utility Closet needs it's own workday for pulling out, sorting, disposal, and reorganizing
    • Ceiling Plug - 
    • Lobby Cases - progress is being made, need more hands.  We can make the next workday all about the Lobby after 3D Printing is done.
    • Electronics/Class Room 
    • Cosplay

Completed Tasks:

In Progress Tasks:

  • Hanging Sign:
    • Sign is assembled.
    • Hardware has been powder coated
    • The protective plastic piece for the top of each section was ordered and now I am just waiting for a warmer day to apply using epoxy and to clear coat it. 

To-Do List:

  • I’d like to make a to-do list for the next SIX workdays that accommodates the moves and helps ease the stress on each steward. Make each one themed maybe?
  • get the front window in the main room fixed
    • need to call landlord, again?
  • Build small table on wheels to go under pegboard in main room
  • Build coatrack or hang coat hooks for raining/cold/snowy days
  • Adhere rubber tiles to floor at bottom of steps

Workday Lists:

Possibility of two workdays a month until the switch-a-roo is done?

  • May
  • June
  • July


Requested To Buy:


Notes:




Progress Photos: